Endra makes final investment decision for Nesse Solar Power Plant and enters into new long-term power agreement with REMA 1000
Endra has decided to invest in and build the Nesse Solar Power Plant in Sveio Municipality and has simultaneously entered into a long-term Power Purchase Agreement (PPA) with REMA 1000. The project will become Norway’s first Agri-PV solar power plant, where renewable energy production is combined with active agricultural operations.
The Nesse Solar Power Plant will have an installed capacity of up to 10.8 MWp and an expected annual production of just under 10 GWh, corresponding to the electricity consumption of approximately 650 households. The power plant is designed for a lifetime of at least 40 years and will provide stable, local, and renewable electricity to the region for decades to come.
– The investment decision for the Nesse Solar Power Plant is an important milestone for Endra. The project combines what we believe the future of solar power development should be: dual land use, local value creation, and long-term industrial partnerships. The fact that REMA 1000 has once again chosen Endra as its partner is a strong endorsement of this model, says Kristian Gautesen, CEO of Endra.
Long-term power agreement with REMA 1000
Through the long-term Power Purchase Agreement, REMA 1000 will purchase all the electricity generated by the Nesse Solar Power Plant. The agreement is Endra’s second PPA with REMA 1000 and builds on the partnership that began with the HIM Solar Power Plant in Vindafjord.
-We are very proud to continue our already strong partnership with REMA 1000 as our customer on this project as well. The Power Purchase Agreement secures a fixed price per unit of energy produced by the power plant, creating the predictability needed to realize the project in a sound and profitable way, says Gautesen.
-At REMA 1000, we want to actively contribute to increasing renewable power production in Norway. Our partnership with Endra gives us access to renewable energy while ensuring that the projects take clear account of nature, land use, and local communities. The Nesse Solar Power Plant is an excellent example of responsible development of new power generation, and we are pleased to help make it a reality, says Kjell Stokbakken, Director of Merchandise & Supply at REMA 1000 Norway and Chairman of REMA Distribution.
-The agreement now entered into between Endra and REMA 1000 demonstrates that long-term industrial customers are looking for more than just a competitive electricity price. They are seeking projects of high quality – technically, environmentally, and socially. The partnership with REMA 1000 provides predictability for the projects and strengthens the development of both Endra and the Norwegian solar power industry, says Pablo Barrera, CEO of Haugaland Kraft and Chairman of Endra.
New solar power project developed in close cooperation with agriculture
The dialogue with the landowner at Nesse Farm began as early as 2023, and the project has been developed in close cooperation with the farm to ensure coexistence between solar power and agriculture. The Nesse Solar Power Plant is planned as Norway’s first Agri-PV project, where the solar installation is combined with sheep grazing in the area.
This enables dual land use in the form of green energy production for society while maintaining food production on the farm. At the same time, the project strengthens the farm’s economic sustainability and helps ensure that the next generation can continue farming. Increased grid capacity and improved access to electricity also provide a foundation for further development of agricultural activities.
– We are incredibly proud of what we are achieving at Nesse. We will continue raising cattle, sheep, and pigs while also producing renewable electricity. The fact that the sheep can graze between the solar panels means a great deal to us – the land continues to be used for food production while we also contribute clean energy. This gives the farm a new economic foundation, and it is exciting to be part of this development. With Endra’s strong local presence in the region and REMA 1000’s focus on responsibility, we feel confident that this will be a strong and long-term partnership, says farmer Maria Nesse.
Low impact development
The solar park covers an area of 146 decares, surrounded by forest and largely screened from view. The project has been developed with minimal visual and environmental impact.
Wildlife corridors will be established to allow animals to pass through the area, and the project also contributes to preserving semi-natural hay meadows, a threatened habitat type in Western Norway.
– The energy projects of the future must create more than just electricity – they must also create local value over time. That is the ambition we aim to realize at Nesse, says Gautesen.
Facts
Location: Nesse, Sveio Municipality, Vestland County
Installed capacity: ~10.8 MWp
Annual production: ~9.5 GWh
Number of solar modules: 16,600
Area: ~146 decares
For further information
Kristian Gautesen, CEO, Endra
Email: [email protected]